Development of CM21 at Ijmuiden:a world class performance

Published online by Cambridge University Press:  23 March 2007

Get access

Abstract

Since 2000 the performance of Corus cold mill 21 has improved substantially. The Overall Equipment Effectiveness (OEE) increased from 33% to 43% and productivity has increased from a level of 1.4 million tonnes in 1999 to nearly 2.0 million tonnes presently. A suitable balance in the triangle of technology, installation and people has proven to be the key prerequisite in this performance increase. The key knowledge areas to operate, maintain and improve the mill are now all available within the production organization.

Type
Research Article
Copyright
© La Revue de Métallurgie, 2007

Access options

Get access to the full version of this content by using one of the access options below. (Log in options will check for institutional or personal access. Content may require purchase if you do not have access.)