Force majeure in the Supreme Court: MUR Shipping BV v RTI Ltd [2024] UKSC 18

Published online by Cambridge University Press:  30 October 2024

Miriam Goldby*
Affiliation:
Queen Mary University of London, London
Rights & Permissions [Opens in a new window]

Extract

Force majeure (FM) clauses are designed to free both parties to a contract from liability when an event beyond their control prevents one or both of them from performing the contract. Examples of such events include inclement weather, natural catastrophes, political upheaval, changes in applicable rules or regulations, or unavailability of essential supplies or services. It is common to include FM clauses in manufacturing, construction or transportation contracts, where there is a high risk of such events occurring due to the length of time required to perform the contract, or the complexity of the performance obligations. Often a lot of money is at stake and pre-allocating the risk of such events is crucial to avoid disputes further down the line. While disputes regarding the meaning and effect of FM clauses may not be unusual, such disputes rarely reach the Supreme Court. MUR Shipping was one such rare case.

Information

Type
Current Developments: Case Comment
Creative Commons
Creative Common License - CCCreative Common License - BYCreative Common License - SA
This is an Open Access article, distributed under the terms of the Creative Commons Attribution-ShareAlike licence (http://creativecommons.org/licenses/by-sa/4.0), which permits re-use, distribution, and reproduction in any medium, provided the same Creative Commons licence is used to distribute the re-used or adapted article and the original article is properly cited.
Copyright
Copyright © The Author(s), 2024. Published by Cambridge University Press on behalf of The Society of Legal Scholars