From hierarchies to markets and partially back again in electricity: responding to decarbonization and security of supply goals

Published online by Cambridge University Press:  15 June 2021

Paul L. Joskow*
Affiliation:
Massachusetts Institute of Technology, Cambridge, MA, USA
*
Corresponding author. Email: pjoskow@mit.edu
Rights & Permissions [Opens in a new window]

Abstract

Electric power sectors around the world have changed dramatically in the last 25 years as a result of sector liberalization policies. Many electricity sectors are now pursuing deep decarbonization goals which will entail replacing dispatchable fossil generation primarily with intermittent renewable generation (wind and solar) over the next 20–30 years. This transition creates new challenges for both short-term wholesale market design and investment incentives consistent with achieving both decarbonization commitments and security of supply criteria. Thinking broadly about the options for institutional change from a Williamsonian perspective – thinking like Williamson – provides a useful framework for examining institutional adaptation. Hybrid markets that combine ‘competition for the market’ that relies on competitive procurement for long-term purchased power agreements with wind, solar, and storage developers, ideally in a technology neutral fashion, and ‘competition in the market’ that relies on short-term markets designed to produce efficient and reliable operations of intermittent generation and storage, is identified as a promising direction for institutional adaptation. Many auction, contract, and market integration issues remain to be resolved.

Information

Type
Research Article
Creative Commons
Creative Common License - CCCreative Common License - BYCreative Common License - NCCreative Common License - SA
This is an Open Access article, distributed under the terms of the Creative Commons Attribution-NonCommercial-ShareAlike licence (http://creativecommons.org/licenses/by-nc-sa/4.0/), which permits non-commercial re-use, distribution, and reproduction in any medium, provided the same Creative Commons licence is included and the original work is properly cited. The written permission of Cambridge University Press must be obtained for commercial re-use.
Copyright
Copyright © The Author(s), 2021. Published by Cambridge University Press on behalf of Millennium Economics Ltd.
Figure 0

Figure 1. Wind generation in ERCOT August 2020 produced using NRGStream Trader 8.1.

Figure 1

Figure 2. Gross and net demand in CAISO August 14 and August 15, 2020. Source: California ISO, Final Root Cause Analysis: Mid-August 2020 Heat Wave, p. 45 (http://www.caiso.com/Documents/Final-Root-Cause-Analysis-Mid-August-2020-Extreme-Heat-Wave.pdf).